Home / Oak Road example
Oak Road Extension, start to finish.
An illustrative £48,000 rear extension, followed through all six stages, one variation and one change request.
£48,000
Agreed project value
6 stages
Each with its own conditions
1 variation
Extra steelwork, +£2,400
£50,400
Final value, paid in full
How each stage played out.
- 3 to 10 March
1. Mobilisation
Stages agreed by both parties. Funding for the first stage confirmed before work began. Site set up and access agreed.
ApprovedPaid£4,800Paid 10 March - 11 March to 1 April
2. Foundations
Builder submitted photos against each condition and the building control inspection record. Homeowner reviewed and approved.
ApprovedPaid£7,200Paid 1 April - 9 April
Variation 003
The engineer asked for extra steel over the rear opening. Builder proposed it with the revised calculation. Homeowner approved, and the extra was funded before Structure started.
Variation approved+£2,400Project now £50,400 - 2 April to 6 May
3. Structure
Walls built and steel installed, including the variation. Approved on submission. Payment showed as processing, then paid.
ApprovedPaid£14,400Paid 6 May - 7 to 29 May
4. Roof and watertight
Roof covered, rooflight fitted, windows and doors in. Approved the morning it was submitted.
ApprovedPaid£9,600Paid 29 May - 30 May to 20 June
5. First fix
Homeowner asked for the electrical test certificate before approving. Builder uploaded it and resubmitted the next morning.
Changes requestedApprovedPaid£7,200Paid 20 June - 21 June to 18 July
6. Completion
Finishes complete and snagging signed off by the homeowner. Final payment made and project record closed.
CompletePaid£7,200Paid 18 July
The project record.
Everything above, kept in one place both parties can download.
Project record
Oak Road ExtensionIllustrative example
| Date | Event | Amount |
|---|---|---|
| 3 Mar | Stages agreed by both parties | £48,000 |
| 10 Mar | Mobilisation approved and paid | £4,800 |
| 1 Apr | Foundations approved and paid | £7,200 |
| 9 Apr | Variation 003 approved | +£2,400 |
| 6 May | Structure approved and paid | £14,400 |
| 29 May | Roof and watertight approved and paid | £9,600 |
| 20 Jun | First fix resubmitted, approved and paid | £7,200 |
| 18 Jul | Completion approved and paid | £7,200 |
| Total paid | £50,400 |